Premium Pre-Starts - Work orders

For issues found when performing a Premium Pre Start, you can convert this issue into a Work Order to manage this issue through to completion, such as setting due date, assigning the work order to users and sending email notifications.

1. For issues found when performing a Premium Pre Start, if further work is required then you can convert this issue into a Work Order. Click on the Pre Start icon to open the report. 

Step 1 image

2. On the Machine Site / Email Report tab, click Manage Issues

Step 2 image

3. Click Create Work Order next to the issue you'd like to assign for action. 

Step 3 image

4. Select a Due Date for the work order to be completed by. 

Step 4 image

5. Select the user you would like to assign the Work Order to. 

Step 5 image

6. If applicable, enter in a cost and the time the job is expected to take. 

Step 6 image

7. Once finished click Save and Send Email to notify the user. 

Step 7 image

8. The saved details are now under Work Orders

Step 8 image

9. To mark an issue as complete, simply tick the complete checkbox. 

Step 9 image

10. And once finished click Save